Joint Development Agreements

Aligning capital and delivery on energy storage projects

In many markets, Joint Development Agreements (JDAs), or equivalent development-stage arrangements, play an important role in the progress of early-stage energy storage projects towards construction and financial investment decision (FID).



JDAs enable investors and project sponsors to commit capital in step with a project's evolution, rather than absorbing the cost of assets that may never reach construction. In return, developers secure capital commitments to continue to progress projects along the lifecycle and are rewarded as they deliver agreed milestones. 

Successful JDA arrangements have several hallmarks:

  • They ensure that the terms and conditions create a genuine symmetry of interest between the parties.
  • They provide projects with a tailored development roadmap.
  • They set the commercial context for the later phases.  

But the development process they govern is inherently unpredictable; no agreement can anticipate every scenario. That's why trust between the parties is one of the crucial differences between success and failure. 

JDAs: A pathway through development

A JDA is an arrangement between investors and developers. Its purpose is to steer an infrastructure project through the greenfield development phase and on to construction. 

When it comes to energy storage assets, the developer initiates the project, and provides the expertise, capabilities, and skillsets to steer it to financial close, including:

  • sourcing and securing the land
  • mapping the project site and grid connection corridor
  • managing relationships with landowners and local communities
  • initiating planning permission and grid connection
  • assessing the overall feasibility of the project 

The investor commits the finance and funding to enable the developer to carry out this work. It will then typically engage in, or lead, the later stages of development, such as procurement and project financing.

The commercial angle: Driving symmetry of interest

Over the past five years, JDAs have increasingly filled a gap in the market for investors and developers in the renewable energy space. They play a critical role in moving projects through early-stage development. 

Under pressure to prove their sustainability credentials, industry players had become accustomed to buying up large portfolios of renewable energy assets in early-stage development. That meant taking on significant holding costs with no guarantee of which projects, if any, would eventually generate returns. When projects stalled – and unfortunately many do – those costs would have to be written off. 

Through a JDA, investors can instead commit capital in stages, as a project hits predefined development milestones. 

For their part, developers take on the obligation to achieve these milestones. They receive phased payments as the project progresses, with part of their return linked to the project reaching construction.

This incentivizes them to see the project through the greenfield phase – increasing the prospects of projects proceeding and bringing returns. 

The result is a symmetry of interest between the parties on each side of the agreement. JDAs align the investment curve with the progress of a project through development: they connect capital deployment directly with delivery. 

They also enable investors to outsource development expertise. For many investors, that’s preferable to recruiting scarce and expensive technical experts in niche areas. The investors get access to the necessary capabilities through the developers without carrying the fixed costs of employing them directly. 

Although a JDA governs only the development phase of the project, its commercial impact extends well beyond it. 

JDAs sit early in a storage project's contractual stack, unlocking vital progress towards the agreements that follow: financing, revenue and commercialization, and construction and supply. Crucially, they set the benchmarks and guardrails for these subsequent arrangements. 

A tailored roadmap: Structuring storage JDAs

Given their purpose is to guide projects through development, a storage JDA is effectively a detailed, project-specific roadmap. For each project, the parties will map out:

  • the current development status
  • the steps needed to reach construction and FID
  • who's responsible for each milestone, and its deadline

If a developer misses a milestone, the investors may have a buyout right. Or they may have the option to walk away, allowing the developer to sell or progress the project themselves, while reimbursing the investor's costs.

The agreement will set out these what-ifs in detail, taking account of a range of factors, including: 

  • grid connection timing
  • whether the project risks going stale
  • the existence of any competing developments nearby
  • the investors’ capital deployment planning
  • the cause of the breach (was it force majeure or the developer’s fault?)

The key challenge: Flexibility in the face of uncertainty

Greenfield development is inherently unpredictable. Applications can throw up unexpected costs or site restrictions, undermining the assumptions a project depends on. 

However carefully a JDA is drafted, it can’t fully anticipate how the project might evolve.

Understandably, however, investors will want clearly defined milestones and fixed payment triggers before committing capital. 

As such, the biggest challenge storage JDAs encounter is the need to flex when the unforeseen happens. How do you build a framework that’s adaptable enough to accommodate change, but also offers the certainty that investors demand? 

The answer lies in trust. Success depends as much on a spirit of genuine partnership and on active relationship management as it does on the wording of the arrangement. 

For example, a developer may be responsible for securing the remaining land required for a site, based on agreed cost assumptions. If individual land costs rise, the developer may still be able to achieve the site acquisition milestone by paying above those assumptions. This may trigger the milestone payment, but it could also undermine the project’s financial viability if the additional cost is not managed.

One way to address this is to build flexibility into the milestone structure. Instead of applying a fixed cap to each individual parcel of land, the parties could agree an overall site acquisition cost threshold. This would give the developer room to secure strategically important parcels where necessary. It would also ensure any overspend is absorbed through the milestone economics, and not passed through in a way that jeopardizes financial close.

What this means for investors and developers

With JDAs playing such a key role in storage project development, what are the practical considerations for the parties involved? How do they ensure the agreement mitigates the main risks and challenges for all concerned? 

This boils down to protecting two sides of the same coin: committed capital for investors, and project progression for developers. 

For investors, it means safeguarding their capital against downside risks at each stage, through mechanisms such as:

  • control rights in the face of material project changes – for example, alterations to project sizing and site layouts  
  • off-ramps for adverse outcomes, such as planning refusal or community opposition
  • appropriate sizing and scaling of milestones that are aligned to the value created as the project moves through the required development stages

Meanwhile, for developers, protecting the project demands flexibility that will allow them to: 

  • keep progressing without the investor continuously intervening in ways that might undermine the milestones
  • take over if the investor withdraws, typically repaying them only once a future liquidity event occurs

Reconciling these priorities is an exercise in threading the needle. JDAs must balance them through careful drafting of the agreement and sizing of the milestones. Tailored advice is crucial to derisking the development phase.

As noted above, however, the contract can’t hardcode every possible scenario. That's why trust between the partners is critical. If trust breaks down, the alternative – buying out the developer and building an in-house development team – is a whole lot costlier. More than any other factor, trust is what determines whether a JDA sees a storage project through development.