Building battery storage at scale
From EPC wrap to split procurement: The changing face of BESS delivery
Why contracting structure matters for BESS projects
Many of the pressure points in Battery Energy Storage System (BESS) projects arise because technical performance, system integration, and operational control do not always sit neatly with a single party. The chosen contracting model therefore has a significant impact on where risk falls.
No one likes to think about disputes during the optimism of project start-up. But parties would be well advised to invest time at the start in understanding how those risks sit within their chosen contracting model and ensuring the contractual framework is drafted to address them coherently.
As explored across our Energy Storage Unlocked series, the key is not just getting individual contracts right but ensuring that the wider contractual framework reflects how the asset will be built, operated, and used to generate revenue.
The emergence of different contracting models
The battery energy storage market is soaring, with global BESS additions projected to exceed 350 GWh in 2026. As the sector evolves, so too do the contracting models used for the construction of these projects.
Full-wrap engineering, procurement, and construction (EPC) contracting remains one route to deliver BESS projects, particularly where developers and lenders are seeking a single point of responsibility and reduced interface risk.
Under this model, a single EPC contractor assumes the primary cost, program, and integration risk. But that risk allocation comes at a premium, and success depends on a contractor having both the requisite expertise in this sector and the financial standing needed to fully support a full turnkey wrap.
Although we are still seeing single EPC wrapping BESS supply and balance of plant in jurisdictions such as Germany, in recent years there has been a shift, certainly in the UK, towards more disaggregated contracting models, including split procurement. Under such models, the developer may contract separately with the battery OEM, the balance-of-plant contractor, and, in some cases, a systems integrator.
To ensure project timelines are met, some developers may also themselves procure long-lead equipment such as transformers upfront and then free-issue to the balance-of-plant contractor, creating an interface risk unless full novation of that supply contract can be agreed. As a result, OEMs are increasingly providing supply-and-install offerings, blurring the traditional distinction between equipment suppliers and construction contractors.
Under a disaggregated model, each contractor is responsible for delivering its scope – still on a fixed lump sum EPC basis, but with overall interface and coordination risk typically sitting with the developer/owner (unless expressly allocated otherwise). As most BESS projects are funded, developers need to mitigate such interface risk as much as possible.
They mitigate the risk in various ways – principally through detailed interface protocols and use of interim key dates for interface deliverables (often with associated liquidated damages), but also through proactive management. To support delivery of the services, a developer/owner might appoint a construction manager or owner's engineer to oversee design, procurement, and site coordination.
But contractual mechanisms are also increasingly being used – with payment withholdings for failure to provide revised programs, progress reports, or remedial measures proposals where progress under the contract falls behind program.
The shift to disaggregated models is essentially a reflection of the supply market split between battery OEMs and EPC (balance of plant) contractors, and a reluctance on the part of battery OEMs to take on full construction risk – or for EPC contractors to take on the risk of performance of the key component, the battery system, which they neither manufacture nor fully control. Given that battery OEMs often insist on limited liability and standardized warranties, the EPC contractor cannot afford to be exposed to risks it cannot fully pass down. The increasing scale and capacity of recent BESS projects also raises questions over the strength of financial covenant of a single EPC contractor for larger capacity projects – even if there were willingness to enter into a single EPC arrangement.
Splitting battery energy storage contracts can have its advantages. As well as reducing solvency risk for developers (and funders), a reduced EPC contractor's risk premium can lower headline project cost. But transferring integration and interface risk to the developer/owner requires careful management.
What contractual considerations are different with BESS projects?
Although many of the contractual considerations will be the same as other energy generation projects, BESS projects have features which give rise to particular issues. BESS assets operate across three functions: charging (importing energy), storage (retaining energy over time), and discharging (exporting energy).
Because a BESS asset is not simply producing energy at a single point in time, performance cannot be assessed by reference to output alone. The contract needs to identify what is guaranteed, how performance is measured, and the operating assumptions on which those guarantees are based. This makes completion testing, performance guarantees and remedies more complex, particularly where different revenue streams depend on different operational behaviours.
Another key issue, regardless of the contracting model adopted, is ensuring that performance guarantees and warranties are properly aligned throughout the supply chain, so that any performance shortfall does not fall into a gap between different contractual regimes.
The new and evolving nature of BESS technology also introduces risks that differ from conventional power generation projects. The allocation of augmentation or replacement costs, for example, is particularly important in BESS projects where battery performance degrades over time.
This can cause issues where a commercial model assumes that a certain level of capacity and efficiency will be maintained across the project life. The contract needs to be clear on the degradation profile, the assumptions on which that is based, and when degradation becomes a contractor issue, an OEM warranty issue, or simply an expected operating cost for the owner.
This becomes more sensitive where the asset is operated aggressively – for example through frequent cycling, high throughput, or revenue stacking, because these actions may accelerate degradation or fall outside the assumptions on which the warranty was priced. Managing warranties is therefore critical to ensuring operational flexibility does not inadvertently undermine warranty protection.
In addition, the trend towards co-located or hybrid projects (where BESS is paired with another asset, such as a renewable energy resource) increases interfaces and operational complexity. Control or operational responsibility of the asset may be fragmented across multiple parties (including the owner, BESS operator, power generator operator, EPC contractor, OEM/system integrator, and grid operator), creating complex interface, governance, and accountability risks.
There can be uncertainty over who has authority to charge, discharge, or modify operating parameters, as well as disputes over responsibility when performance, availability, degradation, grid compliance, cybersecurity, or safety issues arise. So it is important that the contractual structure deals with the allocation of control rights, has clear interface protocols, a robust performance testing regime, carefully structured defect liability and performance guarantee frameworks, and a workable conflict-resolution process – and that all these contractual levers are appropriately aligned across the contract suite.
Where are the pressure points for BESS construction contracts?
A key risk for the construction phase is supply chain constraints across critical minerals, key components and logistics. The supply chain for lithium, cobalt and nickel (which often form part of the battery's core materials) is concentrated in a limited number of jurisdictions and subject to volatile pricing and geopolitical disruption.
Long lead times and shortages for essential equipment (including transformers and other grid-connection hardware) persist. Disruption can lead to re-examination of force majeure clauses in construction contracts for BESS projects. The fragmented nature of BESS supply chains adds further coordination complexity.
These constraints can cause delays and increased cost. As such, stakeholders should identify key interfaces upfront (such as interim interface deliverables and deadlines) and adopt realistic programs, with appropriate incentivization (for example, a mix of payment milestones and interim delay liquidated damages), that take these pressures into account.
This would typically include the use of limited notices to proceed and advance payments to secure long-lead procurement of critical equipment where possible. Grid connection is another issue – in common with other energy projects – as none of the supply chain will take any grid delay risk; it will sit squarely with developers.
Another pressure point is skills shortages. These projects are not only highly specialized but also bring heightened risks around fire safety, system integration, insurance, grid compliance, and multi-party operational interfaces. Delivery will often depend on a relatively small pool of experienced contractors, integrators, and specialists.
At the same time, developers are increasingly assuming a greater coordination role. This requires expertise in systems integration, interface management, and operational planning that sits beyond traditional skillsets. Early engagement of experienced specialists, investment in in-house capability, or strategic partnerships with technology providers can help to mitigate some of these pressures.
Regulatory changes during construction are another pressure point. For example, BESS projects may be affected by evolving environmental rules around fire risk, pollution control, waste handling, and permitting. As rules change, projects may be required to redesign layouts, install additional safety or containment systems, obtain new permits, or revise operational procedures during delivery.
This can give rise to disputes. Developers typically seek to pass these risks to contractors, whereas contractors typically argue that these changes amount to variations or trigger change-in-law provisions. One area of legislative change that developers in the UK are paying particular attention to is the draft Commercial Payments Bill currently going through Parliament, which contains provisions banning the use of retention clauses in construction contracts, alongside wider reforms aimed at tackling late payment practices. This is an area of concern, particularly when there are doubts whether the bond market has sufficient capacity to make up any shortfall in performance security to cover not just the construction phase but also the defects liability period – which, for BESS projects, is typically two years from the start of commercial operation.
Finally, there are the usual construction risks of ground conditions (with contractors unlikely to take on unforeseeable geophysical risks for excavation and foundation activities) and inflationary risk (increasingly being raised by contractors for longer duration projects).